In-Wall
Cost for 2008* |
| General
Comparisons in Cost per Square Foot Including Overhead & Profit |
Unit
Size based on 8” Height X 16” Length
(except where noted) |
2”
Bed
Depth |
4”
Bed
Depth |
6”
Bed
Depth |
8”
Bed
Depth |
STRUCTURAL
GLAZED FACING TILE
Structural Glazed Facing Tile**
(R042126.10-0020 to 3150)
Total Square Foot Cost:
(8” x 16” Face Size-8W Series)
(8” x 8” Face Size-4W Series)
(5-1/3” x 12” Face Size-6T Series) |
14.20
15.55
16.95
|
15.15
15.80
18.50
|
19.10
19.35
23.50
|
21.50
25.50
29.00
|
THIN
SET CERAMIC TILE ON C.M.U.
Thin Set Ceramic 4-1/4” X 4-1/4” Tile on C.M.U.
C.M.U. Installed
(R042210.14-0050/0200/0300/0350)
Tile w/ Thin Set Adhesive (R093013.10-5400)
Mortar Set Adhesive, Add (R093013.10-7300)
Total Square Foot Cost** |
5.95
6.55
2.68
15.18 |
6.25
6.55
2.68
15.48 |
7.15
6.55
2.68
16.38 |
7.80
6.55
2.68
17.03 |
EPOXY
PAINTED C.M.U.
C.M.U. installed
(R042210.14-0050/0200/0300/0350)
Block Filler (R099123.72-4000)
Epoxy Coatings Min. to Max.
(R099656.20-0300/0400)
Total Square Foot Cost |
5.95
1.08
1.16-3.57
8.19-10.60
|
6.25
1.08
1.16-3.57
8.49-10.90 |
7.15
1.08
1.16-3.57
9.39-11.80 |
7.80
1.08
1.16-3.57
10.04-12.45 |
CONCRETE
BLOCK, DECORATIVE
Ground Face (R042210.23-2600/2650/2700)
Total Square Foot Cost
Special Color (R042210.23-2900/2950)
Total Square Foot Cost
|
N/A
N/A
|
10.85
11.47-12.82
|
12.55
13.46-15.23
|
14.05
15.07-17.12
|
Add CMU
Waterproofing Sealer Ext. 2 coats (R099113.90-xxxx)
Brushed (R-0390/0400) =
1.41
Rolled (R-0430/40) =
0.90
Sprayed (R-0470/80) = 0.78
Add CMU Interior Sealer (R099123.72-4100/3600/3620)
Silicone
2 coats sprayed = .49
3 coats glaze sprayed >clear =
1.11
3
coats glaze sprayed >multicolor =
1.55
Add (R099123.72-8200/8300) For
sealer work between 8’ – 15’ add +10%; above
15’ add +20%
|
PREFACED
C.M.U.
Glazed
C.M.U.**
(R042210.44-0100/0200/0250/0300)
Total Square Foot Cost |
14.70 |
15.05 |
16.00 |
17.10 |
*National
averages taken from
Means Building Construction Cost Data 2008, Copyright
Reed Construction Data, Kingston, MA 781-585-7880; All rights reserved.
**For epoxy joints (R042126.10-3300), add $1.61
Disclaimer:
The Ceramic Glazed Masonry Institute (CGMI) believes the numbers in
the above table are true, based upon the R.S. MEANS information. CGMI
makes no guarantee, expressed or implied, as to the accuracy of the
information.